Engineering Consultancy to select suppliers, vet personnel, manage installation, manage QA/QC, manage EHS, control the schedule and overall cost, oversee pre-commissioning/commissioning process. RR Projects is majority share holder in the consortium to build the Lumcloon Power Station and is responsible for FEED/PMC. ...
Scope included Selection of supplier, vetting of personnel, project managed installation, QA/QC, management of the project, management EHS, supervision of pre-commissioning/commissioning process. Handover. Professional personnel provided: • Project Manager • Technical Manager • Civil Works Manager • Pipi...
Description of actual services provided by the BIDDER’s staff: Scope of work included the management of EPC bid requests, evaluation of bids received, and coordination of EPC contractors’ work throughout the project, such as: • Project management • Comprehensive project planning, scheduling, and reporting ...
Dismantling and Erection of Piping and Valves of the Generator Auxiliary Systems Senior staff involved and functions performed: • Project Management • Piping Manager • QA/QC Management • Electrical/C&I Manager • Commissioning Management...
• We carry out annual outage maintenance. • Carried out valve repairs with our own in-situ valve repair machine ...
• We carry out annual outage maintenance. • Carried out valve repairs with our own in-situ valve repair machine....
R&R Mechanical’s has been involved on this project during 2005 with both the constructor, Foster Wheeler and the operator, ESB. • We installed the primary and secondary air fan systems during construction. • We carry out annual outage maintenance on the fuel handling conveyors....
In 2010 R&R Mechanical were awarded the contract to install the Turbogenerator Set for Waste to Energy Facility at La Collette in St. Helier Jersey. Turnkey including electrical , pipework, pre-commissioning, Completed ahead of schedule 1st week July 2010...
R&R Mechanical were involved on this project during 2006 and 2007. Our construction client was Mitsubishi, while the plant PSCS was Shanahan Engineering. We provided 30 staff during phase 2. Activities included: • Install CCCW (Closed Circuit Cooling Water) • Install TCA (Turbine Cooling Air) skid and associated...
R&R Mechanical erected the GEA manufactured Air Cooled Condenser for this project. We have been involved on this project during 2002....
RR Projects has been involved with this project from construction commencement in 2005. We continue to be the contracted provider to mana...
RR Projects has been involved on this project from the construction commencement in 2008 being contracted to erect and as...