Archives

Archive for September, 2013

|

Ferrybridge Power Station – Hitachi Zoosen Inova

Wednesday, September 25th, 2013

RR Projects have been awarded two contracts to fulfil on the Ferrybridge Project:

1. To install the Air Cooled Condenser on the Ferrybridge site. This is a recognition of the quality and experience that RR Projects has in erecting ACC technology. The erection of this ACC falls under the EU requirement to issue a CE mark, which RR Projects has obtained through its compliance and operation to EN 1090-1.

2. RR Projects, in contract with ROBA Rohr + Anlagenbau GmbH, will perform the complete mechanical erection of the WSC piping systems for the Ferrybridge project.

Both projects commence in October 2013

Posted in projects


RR Projects obtains the right to issue the CE Mark

Wednesday, September 25th, 2013

Following a Compliance audit by TUV Rheinland, RR Projects are authorised to issue the CE Mark for erecting steel structures. This comes about as a result of complying with EN1090-1. As a major part of EN1090 requires quality welding, RR Projects applied to TUV Rheinland for and gained accreditation to ISO 3834.

In order to obtain the CE Mark, all structural metallic components for the execution of structures, are now required to be certified to EN 1090-2. Being qualified to issue this mark, which is mandatory across the European Union area, an organisation must be accredited to EN 1090-2. CE Marking for all construction products, covered by a harmonised European standard or conforming to a European Technical Assessment, became mandatory on 1 July 2013. For fabricated structural steelwork, CE Marking will become mandatory on 1 July 2014.

Being an erector of Air Cooled Condensers (ACCs), this is particularly relevant to RR Projects. We are now qualified to certify that the completed structure is in compliance with all of the legal requirements of its erection.

Posted in featured, latest news


RR Projects wins two contracts at Ferrybridge Power Station

Tuesday, September 24th, 2013

Hitachi Zosen Inova was appointed the general contractor in the construction of the multifuel plant at SSE’s Ferrybridge power station in West Yorkshire, UK. It will generate electricity by thermal waste treatment. RR Projects have been awarded the contract to install the Air Cooled Condenser on the Ferrybridge site. This is a recognition of the quality and experience that RR Projects has in erecting ACC technology. The erection of this ACC falls under the EU requirement to issue a CE mark, which RR Projects has obtained through its compliance and operation to EN 1090-1.

In further news, RR Projects, in contract with ROBA Rohr + Anlagenbau GmbH, will perform the complete mechanical erection of the WSC piping systems for the Ferrybridge project. This project has come about due to the standard of workmanship and welding excellence that RR Projects deliver.

Posted in featured, latest news